A company wants all new projects to inherit baseline IAM, networking constraints, and audit settings. What should it use?

  1. AOrganization policies and automation
  2. BIndividual user scripts
  3. CManual setup per project
  4. DOnly labels
Show answer

Answer: A

Organization policies plus automation provide scalable baseline governance for new projects.